Tendering for construction projects is a complex activity that requires an extensive exchange of important information. In addition to project drawings, the tender documentation includes a number of additional documents, conditions, contracts and other requisites that define the contents and scope of the project. This article aims to analyse the method of tendering for a private investor’s multifunctional building project and proposes a variant of a solution employing a different method. Specifically, the methods are Design-Build (DB) and Design-Bid-Build (DBB). The article focuses exclusively on the preparation and the project tendering itself. It does not cover profitability calculations at the pre-investment stage or construction management after the construction contract is signed. The results show noticeable differences between the aforementioned methods. In particular, there are significant differences in terms of the time necessary to prepare the project documentation. The DB method would be more efficient and economical in this respect. Nevertheless, the investor opted for the DBB method in view of potential modifications required by clients and probably also due to a degree of distrust of the DB method, with which it had no prior experience

Anglický abstrakt

Tendering for construction projects is a complex activity that requires an extensive exchange of important information. In addition to project drawings, the tender documentation includes a number of additional documents, conditions, contracts and other requisites that define the contents and scope of the project. This article aims to analyse the method of tendering for a private investor’s multifunctional building project and proposes a variant of a solution employing a different method. Specifically, the methods are Design-Build (DB) and Design-Bid-Build (DBB). The article focuses exclusively on the preparation and the project tendering itself. It does not cover profitability calculations at the pre-investment stage or construction management after the construction contract is signed. The results show noticeable differences between the aforementioned methods. In particular, there are significant differences in terms of the time necessary to prepare the project documentation. The DB method would be more efficient and economical in this respect. Nevertheless, the investor opted for the DBB method in view of potential modifications required by clients and probably also due to a degree of distrust of the DB method, with which it had no prior experience

Klíčová slova

Project management; risks of tender documentation; construction projects

Klíčová slova v angličtině

Project management; risks of tender documentation; construction projects

Autoři

MIKULÍK, M.; HROMÁDKA, V.

Rok RIV

2024

Vydáno

27.09.2023

Nakladatel

AIP Publishing

Místo

Melville, USA

Kniha

World Multidisciplinary Civil Engineering-Architecture-Urban Planning Symposium - WMCAUS 2022

ISSN

1551-7616

Periodikum

AIP conference proceedings

Svazek

2023

Číslo

2928

Stát

Spojené státy americké

Strany od

1

Strany do

10

Strany počet

10

URL

BibTex

@inproceedings{BUT185240,
  author="Michal {Mikulík} and Vít {Hromádka}",
  title="Project management and the risks of tender documentation for construction projects",
  booktitle="World Multidisciplinary Civil Engineering-Architecture-Urban Planning Symposium - WMCAUS 2022",
  year="2023",
  journal="AIP conference proceedings",
  volume="2023",
  number="2928",
  pages="1--10",
  publisher="AIP Publishing",
  address="Melville, USA",
  doi="10.1063/5.0170904",
  issn="0094-243X",
  url="https://watermark.silverchair.com/130018_1_5.0170904.pdf?token=AQECAHi208BE49Ooan9kkhW_Ercy7Dm3ZL_9Cf3qfKAc485ysgAABYkwggWFBgkqhkiG9w0BBwagggV2MIIFcgIBADCCBWsGCSqGSIb3DQEHATAeBglghkgBZQMEAS4wEQQMCkLsIAul5VkjIG-PAgEQgIIFPAnXLyjC1d7Z5ImHnH8oyAc4g67aOGUh40NP963a9zZwkFGocqBiKe957g5a02IXbbOFTh_yHh9zLvEo4iF08DZUZqmCzg4eIm84HEmrcavUDfArq-rxv5rZP173y2jkkqOYzdJvzRzwKBr0jjW0SxxrCjx929-ViGOGK7eROVSuv9d7XIvxJ3Lu-hjlQx0Rp0MkT1h-D20aJz25h4WpAw6l8Co7aktm8xJb4YgNiiCM0MHuS4OBUK4LOfLK8RwfuaRmhqafDDSDejGtcYHhy8ZqjwQ6EOfFx8vcb"
}