Přístupnostní navigace
E-přihláška
Vyhledávání Vyhledat Zavřít
Detail publikačního výsledku
DOSKOČIL, R.; DOUBRAVSKÝ, K.
Originální název
Implementation of the PERT Method in MS Excel
Anglický název
Druh
Stať ve sborníku v databázi WoS či Scopus
Originální abstrakt
The paper deals with a time and probabilistic analysis of PERT network graphs. The paper describes the implementation of the traditional PERT algorithm for finding the probabilistic analysis, the node and activity criticality by use of software MS Excel. The paper shows how relative comfortably to work with the PERT method. Benefit of this approach evaluate especially end-users. Case study describes a project which includes 14 subactivities. The completion time of each activity is not know certainly (only estimates are available). Model of the project consists of a network graph, which comprises 18 activities (4 fictitious activities) and 14 nodes. These data serve as inputs for spreadsheet in MS Excel. The program can be used to solve various large projects.
Anglický abstrakt
Klíčová slova
PERT method, MS Excel, time analysis, probability analysis, node criticality
Klíčová slova v angličtině
Autoři
Rok RIV
2013
Vydáno
09.05.2012
Nakladatel
International Business Information Management Association
Místo
Istanbul, Turkey
ISBN
978-0-9821489-7-6
Kniha
Innovation and Sustainable Economic Competitive Advantage
Strany od
1262
Strany do
1271
Strany počet
10
BibTex
@inproceedings{BUT93049, author="Radek {Doskočil} and Karel {Doubravský}", title="Implementation of the PERT Method in MS Excel", booktitle="Innovation and Sustainable Economic Competitive Advantage", year="2012", number="18", pages="1262--1271", publisher="International Business Information Management Association", address="Istanbul, Turkey", isbn="978-0-9821489-7-6" }