Course detail
Selected sections of building technology processes - GP
FAST-CW54Acad. year: 2009/2010
The first part the course covers the study of selected construction processes linked with carcass and interior and finishing processes at the realization of the building constructions. It is dealing with technology, space and time structure, mutual links, requirements for the site preparation, principles of the execution of construction processes and respective quality requirements. In the part dealing with execution of building construction technologies of special construction foundation for excavated underground constructions are given. Further a summary of classical and modern tunnelling systems and assemblies, machines and equipment for building of underground constructions is presented.
Language of instruction
Number of ECTS credits
Mode of study
Guarantor
Department
Learning outcomes of the course unit
Prerequisites
Co-requisites
Planned learning activities and teaching methods
Assesment methods and criteria linked to learning outcomes
Course curriculum
2.Principles of technology procedures at execution of earthworks.
3.Execution of utilities and roads. Mechanization of construction processes, definitions, tasks and stage of mechanization. Capacity of machines and machine assemblies, basic division.
4.Principles of walling made of bricks, shaped bricks and stone. Module, technology and quality requirements. Quality control.
5.Installation procedures. Interior drains. Water and central heating distributions. Execution of building insulations against water, heat, noise, vibrations and chemical impacts. Flowcharts, readiness of the building, links, tests and quality inspections.
6.Building structures surface treatment – interior and exterior plasters, types, flowcharts, preparation of the base, technology intervals, flatness requirements, quality control.
7.Technology of works of special construction foundation related with the excavated underground constructions.
8.Supporting of building structures and jet injections.
9.Casing structures (Stent Walls, pilot and underground walls).
10.Injections and anchoring of the rock environment.
11.Nomenclature of underground structures – types, division. Tunnel systems and arrangements.
12.Ring (curb) method. New Austrian tunnelling method. Method of a peripheral notch method. Micro-tunnelling.
13.Machines and equipment for construction of underground constructions (cut, excavated, micro-tunnelled).
Work placements
Aims
Specification of controlled education, way of implementation and compensation for absences
Recommended optional programme components
Prerequisites and corequisites
Basic literature
Klepsatel,F.,Kusý,P.,Mařík,L.: Výstavba tunelů ve skalních horninách. JAGA Bratislava, 2003.
Kudrna,J.: Technologie pozemních komunikací. VUT v Brně, FAST, 2007.
Lízal,P. a kol.: Technologie stavebních procesů pozemních staveb. Cerm,s.r.o. Brno, 2003.
Motyčka,V. a kol.: Technologie staveb I, Technologie stavebních procesů, část 2, Hrubá vrchní stavba. Cerm,s.r.o. Brno,, 2005.
Recommended reading
Classification of course in study plans