Course detail
Realisation of water structures
FAST-CR02Acad. year: 2014/2015
Planning, designing and realization development of structures. Preparation work at a site. Rock and earthwork, special foundation engineering. Carpenter and cabinetmaker works, boarding of the structures and elements, concrete work - concrete production, transport, deposition and tending.
Digging of a tube ditch, trenchless technology, pipe work. Transport in and out of the site. Operational and social equipment of the site, construction yard and line structures site organization. Main responsibility of technical stuff and works foreman during the construction phase, occupational safety. Operational evidence of the structures.
Language of instruction
Number of ECTS credits
Mode of study
Guarantor
Department
Learning outcomes of the course unit
Rock and earthwork – cubage determination, construction technology, deployment of mechanisms, accomplishment calculation
Concrete work – division of operating and dilatation block Technology of realization, deployment of mechanisms
Design of site equipment, site transport design
Building works schedule assembly, safety regulations
Prerequisites
Co-requisites
Planned learning activities and teaching methods
Assesment methods and criteria linked to learning outcomes
Course curriculum
2. Design of open foundation pit
3. Coffer dam, site drainage, site pumps
4. Rock and earthwork – cubage determination, construction technology, deployment of mechanisms, accomplishment calculation
5. Concrete work – division of operating and dilatation block Technology of realization, deployment of mechanisms
6. Site transport design
7. Design of site equipment
8. Finishing works
9. Building works schedule assembly
10. Safety regulations
Work placements
Aims
Specification of controlled education, way of implementation and compensation for absences
Recommended optional programme components
Prerequisites and corequisites
Basic literature
Rýznar,J.,Smrček,M.: Mechanizace a provádění staveb. VUT Brno, 1986. (CS)
Recommended reading
Šlezingr, M., Úradníček, L.: Bankside treees and shrubs. CERM Brno, 2003. (EN)
Classification of course in study plans
Type of course unit
Lecture
Teacher / Lecturer
Syllabus
2. Design of open foundation pit
3. Coffer dam, site drainage, site pumps
4. Rock and earthwork – cubage determination, construction technology, deployment of mechanisms, accomplishment calculation
5. Concrete work – division of operating and dilatation block Technology of realization, deployment of mechanisms
6. Site transport design
7. Design of site equipment
8. Finishing works
9. Building works schedule assembly
10. Safety regulations
Exercise
Teacher / Lecturer
Syllabus
2. Design of open foundation pit
3. Site drainage, site pumps
4. Rock and earthwork – cubage determination, construction technology, deployment of mechanisms, accomplishment calculation
5. Concrete work – division of operating and dilatation block Technology of realisation, deployment of mechanisms
6. Site transport design
7. Design of site equipment
8. Finishing works
9. Building works schedule assembly
10. Safety regulations