Comparison of the planned and actual course of construction of reinforced concrete monolithic structures

DOUBEK, R.

Original Title

Comparison of the planned and actual course of construction of reinforced concrete monolithic structures

English Title

Comparison of the planned and actual course of construction of reinforced concrete monolithic structures

Type

Paper in proceedings (conference paper)

Original Abstract

During construction, there is often a change in contractual terms, either in advance of construction or delayed construction. This phenomenon is due to many influencing factors such as delayed subcontracting, climatic conditions, the surrounding construction site, the quality of project documentation, the solvency of the investor, the expertise of the general contractor, etc. The aim of the paper is to assess the planned and actual construction of reinforced concrete monolithic structural elements using tower cranes. The subject of the paper is to state the expected method of implementation in time and how the construction proceeded. Milestones for accelerating and slowing down construction, analyzing their causes and proposing future measures will be presented. Data are obtained by measuring real buildings.

English abstract

During construction, there is often a change in contractual terms, either in advance of construction or delayed construction. This phenomenon is due to many influencing factors such as delayed subcontracting, climatic conditions, the surrounding construction site, the quality of project documentation, the solvency of the investor, the expertise of the general contractor, etc. The aim of the paper is to assess the planned and actual construction of reinforced concrete monolithic structural elements using tower cranes. The subject of the paper is to state the expected method of implementation in time and how the construction proceeded. Milestones for accelerating and slowing down construction, analyzing their causes and proposing future measures will be presented. Data are obtained by measuring real buildings.

Keywords

Contractual and actual terms, tower cranes, reinforced concrete monolithic construction, construction process

Key words in English

Contractual and actual terms, tower cranes, reinforced concrete monolithic construction, construction process

Authors

DOUBEK, R.

RIV year

2022

Released

13.10.2021

Publisher

IOP Publishing

Location

Košice

Book

13th International Scientific Conference of Civil and Environmental Engineering for PhD. Students and Young Scientists 13-15 October 2021, High Tatras, Slovakia

ISBN

1757-899X

Periodical

IOP Conference Series: Materials Science and Engineering

Volume

1209

Number

1

State

United Kingdom of Great Britain and Northern Ireland

Pages from

1

Pages to

6

Pages count

6

URL

Full text in the Digital Library

BibTex

@inproceedings{BUT176459,
  author="Rostislav {Doubek}",
  title="Comparison of the planned and actual course of construction of reinforced concrete monolithic structures",
  booktitle="13th International Scientific Conference of Civil and Environmental Engineering for PhD. Students and Young Scientists 13-15 October 2021, High Tatras, Slovakia",
  year="2021",
  journal="IOP Conference Series: Materials Science and Engineering",
  volume="1209",
  number="1",
  pages="1--6",
  publisher="IOP Publishing",
  address="Košice",
  doi="10.1088/1757-899X/1209/1/012011",
  url="https://iopscience.iop.org/article/10.1088/1757-899X/1209/1/012011"
}

Documents